Consider the following proposed solution for the critical section problem. There are nn processes : P0....Pn−1P_0....P_{n-1}. In the code, function pmax\text{pmax} returns an integer not smaller than any of its arguments .For all i,t[i]i,t[i] is initialized to zero.

Code for PiP_i;

do {
    c[i]=1; t[i]= pmax (t[0],....,t[n-1])+1; c[i]=0;
    for every j != i in {0,....,n-1} {
        while (c[j]); 
        while (t[j] != 0 && t[j] <=t[i]);
    }
    Critical Section;
    t[i]=0;
    
    Remainder Section;
    
}  while (true);

Which of the following is TRUE about the above solution?

  1. A
    At most one process can be in the critical section at any time
    Correct answer
  2. B
    The bounded wait condition is satisfied
  3. C
    The progress condition is satisfied
  4. D
    It cannot cause a deadlock

Answer

(A) At most one process can be in the critical section at any time

Approach

The code is a modified Lamport bakery algorithm. The key points are the choosing flag c[i], the ticket value t[i] returned by pmax, and the waiting condition while(t[j] != 0 &amp;&amp; t[j] &lt;= t[i]). Because pmax may return the same maximum to multiple processes, ticket ties are possible, and the condition &lt;= makes tied processes wait on each other. Analyze mutual exclusion, progress, bounded waiting, and deadlock accordingly.

The solution preserves mutual exclusion because a process can enter only if its ticket is strictly smaller than the nonzero tickets of all others; two processes cannot both satisfy this. However, ties in the pmax-based ticket assignment can make multiple processes wait on each other, causing deadlock, violating progress, and violating bounded waiting. Hence the only true statement is A.