ISRO Scientist/Engineer CSE 2017 PYQ: Consider the following scheduling: A. Gang scheduling s. Guaranteed scheduling B. Rate monotonic scheduling…

Consider the following scheduling:

A. Gang scheduling s. Guaranteed scheduling
B. Rate monotonic scheduling t. Thread scheduling
C. Fair share scheduling u. Real-time scheduling

Matching the table in the order $A,B,C$ gives

  1. A
    t,u,s
    Correct answer
  2. B
    s,t,u
  3. C
    u,s,t
  4. D
    u,t,s

Answer

(A) t,u,s

Approach

Match each scheduling technique on the left (A, B, C) with its correct description on the right (s, t, u) using the defining property of each technique, then read off the resulting sequence.