Skip to content

Paper II · Unit 6: Software Engineering

Estimation and Scheduling of Software Projects

Estimation and Scheduling of Software Projects is a topic inside Unit 6 (Software Engineering) of UGC NET Computer Science and Applications, Paper II (code 87). GateIQ has published 39 questions classified under this topic — 14.6% of everything recorded in this unit, and 39 of them carry a written solution.

What this topic covers

Software Sizing, LOC and FP based Estimations; Estimating Cost and Effort; Estimation Models, Constructive Cost Model (COCOMO), Project Scheduling and Staffing; Time-line Charts

Syllabus wording above is the official heading for this topic; the question counts are GateIQ’s own classification of its published archive.

Try Estimation and Scheduling of Software Projects PYQs free

Attempt the 5 most recent published questions on this topic right here, with the published answer and explanation after each check. No account is needed and nothing is saved. Practice tracking and analytics are part of UGC IQ.

0 of 5 checked
  1. 1Previous year question

    Which Metrics are derived by normalizing quality and/or productivity measures by considering the size of the software that has been produced?

    Choose an option to check it.
  2. 2Previous year question

    Size and complexity are a part of

    Choose an option to check it.
  3. 3Previous year question

    A Software project was estimated at 864 Function Points. A six person team will be assigned to project consisting of a requirement gathering person, one designer, two programmers and two testers. The salary of the designer is Rs. 70,000\text{Rs. } 70,000 per month, requirement gatherer is Rs. 50,000\text{Rs. } 50,000 per month, programmer is Rs. 60,000\text{Rs. } 60,000 per month and a tester is Rs. 60,000\text{Rs. } 60,000 per month. Average productivity for the team is 12 FP per person month. Which of the following represents the projected cost of the project

    Choose an option to check it.
  4. 4Previous year question

    A company has a choice of two languages L1L_1 and L2L_2 to develop a software for their client. Number of LOC required to develop an application in L2L_2 is thrice the LOC in language L1L_1. Also, software has to be maintained for next 10 years. Various parameters for two languages are given below to decide which language should be preferred for development.

    PARAMETERL1L2Man-year needed for developmentLOC/1000LOC/1000Development costRs.70,000Rs.90,000Cost of Maintenance per yearRs.1,00,000Rs.40,000\begin{array}{|l|l|l|} \hline \text{PARAMETER} & L_1 & L_2 \\ \hline \text{Man-year needed for development} & \text{LOC}/1000 & \text{LOC}/1000 \\ \hline \text{Development cost} & \text{Rs}. 70,000 & \text{Rs}. 90,000 \\ \hline \text{Cost of Maintenance per year} & \text{Rs.} 1,00,000 & \text{Rs.} 40,000 \\ \hline \end{array}

    Total cost of project include cost of development and maintenance. What is the LOC\text{LOC} for L1L_1 for which cost of developing the software with both languages must be same?

    Choose an option to check it.
  5. 5Previous year question

    An _______ chart is a project schedule representation that presents project plan as a directed graph. The critical path is the __________ sequence of ________ tasks and it defines project ________.

    Choose an option to check it.

34 more questions on Estimation and Scheduling of Software Projects

These 5 are free to try without an account. The rest of the published questions on Estimation and Scheduling of Software Projects are part of UGC IQ: see what it includes, or create an account to get started.

Estimation and Scheduling of Software Projects: questions people ask

How many UGC NET Computer Science questions are asked on Estimation and Scheduling of Software Projects?

GateIQ has published 39 UGC NET Computer Science previous year questions on Estimation and Scheduling of Software Projects, and 39 of them carry a written solution. That is 14.6% of the questions in Unit 6, Software Engineering.

Which unit of UGC NET Computer Science Paper 2 is Estimation and Scheduling of Software Projects in?

Estimation and Scheduling of Software Projects is a topic of Unit 6, Software Engineering, in Paper II (Computer Science and Applications, code 87).

Can I practise Estimation and Scheduling of Software Projects PYQs for free?

Yes. The 5 most recent published questions on this topic are free on this page with no signup, and each shows the published answer with its explanation. The full archive, practice tracking and analytics are part of UGC IQ.

Related topics in Unit 6

Full syllabus · Paper II overview