Identify the correct order of the following five levels of Capability Maturity Model (from lower to higher) to measure the maturity of an organization's software process.
- Defined
- Optimizing
- Initial
- Managed
- Repeatable
Choose the correct answer from the options given below
- A$\text{III, I, V, IV, II}$
- B$\text{III, II, IV, V, I}$
- C$\text{III,V, I, II, IV}$
- D$\text{III, V, I, IV, II}$Correct answer
Answer
(D) $\text{III, V, I, IV, II}$
Approach
Order the CMM levels from lowest to highest and map them to the numerals.