UGC NET CS 2023 PYQ: Match List I with List II List I List II A. PERT I. used for nonrepetitive jobs B. Optimistic time II. Used…
Match List I with List II
| List I | List II |
| A. PERT | I. used for nonrepetitive jobs |
| B. Optimistic time | II. Used for repetitive jobs |
| C. CPM | III. The shortest possible time to complete the activity if all goes well. |
| D. Pessimistic time | IV. The longest time that an activity takes |
Choose the correct answer from the options given below:
- A$\text{A-III B-IV C-II D-I}$
- B$\text{A-IV B-I C-I D-III}$
- C$\text{A-I B-III C-II D-III}$
- D$\text{A-I B-III C-II D-IV}$Correct answer
Answer
(D) $\text{A-I B-III C-II D-IV}$
Approach
Recall the standard definitions of PERT, CPM, optimistic time and pessimistic time in project scheduling.