UGC NET CS 2023Discrete Structures and Optimization › OptimizationVerified

UGC NET CS 2023 PYQ: Match List I with List II List I List II A. PERT I. used for nonrepetitive jobs B. Optimistic time II. Used…

Match List I with List II

List I List II
A. PERT I. used for nonrepetitive jobs
B. Optimistic time II. Used for repetitive jobs
C. CPM III. The shortest possible time to complete the activity if all goes well.
D. Pessimistic time IV. The longest time that an activity takes


Choose the correct answer from the options given below:

  1. A
    $\text{A-III B-IV C-II D-I}$
  2. B
    $\text{A-IV B-I C-I D-III}$
  3. C
    $\text{A-I B-III C-II D-III}$
  4. D
    $\text{A-I B-III C-II D-IV}$
    Correct answer

Answer

(D) $\text{A-I B-III C-II D-IV}$

Approach

Recall the standard definitions of PERT, CPM, optimistic time and pessimistic time in project scheduling.