UGC NET CS 2019 PYQ: An _______ chart is a project schedule representation that presents project plan as a directed graph. The…

An _______ chart is a project schedule representation that presents project plan as a directed graph. The critical path is the __________ sequence of ________ tasks and it defines project ________.

  1. A
    Activity, Shortest, Independent, Cost
  2. B
    Activity, Longest, Dependent, Duration
    Correct answer
  3. C
    Activity, Longest, Independent, Duration
  4. D
    Activity, Shortest, Dependent, Duration

Answer

(B) Activity, Longest, Dependent, Duration

Approach

Recall the definition of an activity (PERT/CPM) chart and the critical path in project scheduling.