Skip to content

UGC NET CS 2020Software Engineering › Estimation and Scheduling of Software ProjectsVerified

UGC NET CS 2020 PYQ: A Software project was estimated at 864 Function Points. A six person team will be assigned to project…

A Software project was estimated at 864 Function Points. A six person team will be assigned to project consisting of a requirement gathering person, one designer, two programmers and two testers. The salary of the designer is $\text{Rs. } 70,000$ per month, requirement gatherer is $\text{Rs. } 50,000$ per month, programmer is $\text{Rs. } 60,000$ per month and a tester is $\text{Rs. } 60,000$ per month. Average productivity for the team is 12 FP per person month. Which of the following represents the projected cost of the project

  1. A
    $\text{Rs. } 33,20,000$
  2. B
    $\text{Rs. } 43,20,000$
    Correct answer
  3. C
    $\text{Rs. } 33,10,000$
  4. D
    $\text{Rs. } 22,10,000$

Answer

(B) $\text{Rs. } 43,20,000$

Approach

Compute duration from size and team productivity, then multiply by the monthly team salary bill.

Reviewed by UGC IQ Editorial Team.